Project Overview
The latest monthly progress reports – February 2026 and March 2026 – for the Anniston PCB Site are now available.
Residential
Informational devices will be submitted to property owners and tenants participating in the Interim Institutional Control Program for residential properties where PCBs may be present.
These materials are intended to:
- Provide clear property information
- Support awareness and compliance
- Ensure ongoing protection of residents
Nonresidential
Solutia submitted the Preliminary Remedial Design for:
- Soil
- Sediment and creek banks
- T-11 area
Solutia will begin preparation of the pre-final design after
receiving feedback from the EPA.
Eastman plant site
Recent reports document:
- Institutional controls at the plant
- Operational improvements to the existing groundwater system
These updates support continued environmental protection and
system optimization.
Choccolocco Creek
Fish Tracking Study – Spring 2026
Beginning in Spring 2026, Solutia will initiate a fish tracking study to better understand fish movement within Choccolocco Creek.
Species included in the study:
- Bass
- Catfish
- Crappie / Sunfish
Fish will be fitted with small tags. Monitoring stations will be placed around the creek to record movement patterns.